Slow progress in WGH power project

Date:

Share post:

spot_imgspot_img

SHILLONG: The construction of the 33KV S/C line from Rongkhon to Dadenggre is making slow progress leading to a delay in improved power supply in the area.
The monthly progress report of the North Eastern Council (NEC) for July says only 5 percent work on the Improvement of Power Supply project, which was sanctioned in March 2016, is complete. Besides the S/C line, the project also includes strengthening of the 11KV and LT network under West Garo Hills (D) division.
The deadline for the Rs 570-lakh project is March 2018. The share of NEC is Rs 513 lakh and the state government has to contribute Rs 57 lakh.

spot_imgspot_img

Related articles

Today in City

The Chief Justice of the High Court of Meghalaya, Justice Revati Mohite Dere, will lay the foundation stone...

MCA sexual harassment row: Sports Minister defends dismissal of coach

SHILLONG, June 29: Sports and Youth Affairs Minister Wailadmiki Shylla has backed the Meghalaya Cricket Association’s (MCA) decision...

High Court acquits driver in 11-yr-old city murder case

SHILLONG, June 29: In a significant judgment, the High Court of Meghalaya on Monday acquitted Ashim Sinha, a...

Man killed in Nongpoh hit-and-run

NONGPOH, June 29: A 50-year-old man was killed on the spot after being struck by a speeding truck...