Ganol power project likely to be commissioned by Dec-end

Date:

Share post:

spot_imgspot_img

SHILLONG, March 24: The Ganol Hydro Power project, which has come under the scanner over cost escalation, is likely to be commissioned this year.
An official from the Power department said on Thursday that the power project is due for completion soon and the department was optimistic that the project would be commissioned this year itself.
The project falls under the ambit of the independent inquiry committee, headed by Justice (retd) RN Mishra, which is due to submit its report on or before March 31.
During the recently concluded Assembly session, the All India Trinamool Congress had demanded a specific inquiry into the huge cost escalation of the Ganol Hydro Power Project from Rs 356 crore to Rs 507 crore.
The project with a capacity of 21.5 MW is being implemented in Chibragre, around 15 km from Tura. It will be the first hydro power project in the Garo Hills region.
The project has encountered several delays since it was conceived in 2006.

spot_imgspot_img

Related articles

JCMDA, jolni MLA, MDC-rang baksa koelani bidingo chanchirima

KHLIEHRIAT: Jaintia Coal Miners & Dealers Association (JCMDA), EJH district-ni Khliehriat West Community Hall-o tom·enba coal-mining-ni mamlao chanchirimangaha. Tom·anio...

Chi banako nirokna Mahendraganj CHC, Rapid Response Team-ko bikota

AMPATI: Mahendraganj jolo chi bana a·sel ong·engani gimin duk-neng·nikako ga·akgipa manderangna dakchakna gita Mahendraganj Community Health Centre (CHC),...

Voice that became Kerala’s own: S. Janaki passes away at 88

Thiruvananthapuram, July 12 : For generations of Malayalis, S. Janaki was more than a playback singer, she was...

SGH-o chini sabisi batroroenganina mikrakata

BAGHAMARA: South Garo Hills, Baghamara songjinmao chini sabisi jedake fever/typoid, Diarrhea sanirang batroroenganina Executive Engineer (PHE) RWS, Division,...