Selsella water supply scheme to be complete by March 2021

Date:

Share post:

spot_imgspot_img

SHILLONG, Nov 11: The Greater Selsella Water Supply Scheme, sanctioned during the year 2013-2014 for Rs 1,204 lakh, is under progress.
Informing this during the question hour of the Assembly’s Autumn Session, Minister in charge of PHE, Renikton Tongkhar Lyngdoh, said that the total number of villages, which the scheme is proposed to cover, is 86.
He further informed that the revised estimate cost of the project amounts to Rs 1733.73 lakh and the expected time of completion is March 31, 2021.
Replying to a supplementary query by NPP MLA Ferlin Sangma on the delay of six years in completing the project, the minister said it was due to late payment, while adding that the first instalment was released on December 26 in 2012; second instalment on September 29, 2016; and the third instalment was received on October 9, 2017.

spot_imgspot_img

Related articles

On 10th Muharram, Kashmir makes two loud statements of ‘Kashmiriyat’

Srinagar, July 6: As Jammu and Kashmir Lt Governor Manoj Sinha joined Muslim mourners during the 10th Muharram...

CM Rekha Gupta slams AAP’s health model, terms ‘Mohalla Clinics’ a ‘photo propaganda’

New Delhi, July 6:Delhi Chief Minister Rekha Gupta on Sunday launched a scathing attack on the Aam Aadmi...

MP govt initiates probe in school repair work after irregularities surface on social media

Bhopal, July 6 : A swift and high-level investigation was initiated after a serious case of financial malpractice...

Inspired by PM Modi, UP restaurateur’s ‘Pradhanmantri Chaiwala’ grabs spotlight

New Delhi, July 6 : While several roadside eateries and dhabas along the Kanwar Yatra route are under...