Monsoon delays Rilbong-Upper Shillong Road construction

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, Sep 17: The National Highways & Infrastructure Development Corporation Ltd (NHIDCL) is waiting for the monsoon to retreat in order to expedite the construction of package-I of the Shillong-Dawki Road.
The package-I will be a four-lane road from Rilbong till Upper Shillong.
“The rainy season has slowed down the work but we are still committed to complete the package-I within December this year,” an NHIDCL official said, adding that no bituminous work can be carried out during the rainy season.
However, the NHIDCL has focused on completing the structural work which is nearing 95% completion.
The overall physical progress of the package-I is around 70 per, the official said.

spot_imgspot_img

Related articles

PMGSY ramako taridapjani gimin jolo songdongenggipa manderang sing·doa

KHARKUTTA: North Garo Hills a·jao, Baksalpara-oni Bagabata-ona tarianggipa PMGSY rama nosto ong·ani ja·man, ia ramako bilsi bongana nirokchina...

Wachio buringni me·gimuko cha·jachina sorkari mikrakata

AMPATI: Ia sal somoirangara wachini somoi ong·engani gimin buringo man·gipa me·gimurangko skatang cha·jachina aro manderangni jakkalenggipa chirangko skatang...

MRSSA-ko bon·chipatnasa sorkari ‘pa·sikchaenga’ ine KSU matnanga

2016 bilsini MRSSA-kon jakkalchina sorkariko didia SHILLONG: Right to Information (RTI) ka·e am·sandianirangko dakon, Home Affairs Ministry aro kachariba,...