Concrete surface work begins on Umiam dam

Date:

Share post:

spot_imgspot_img

By Our Reporter

SHILLONG, June 12: In an effort to speed up the Umiam dam repair work and to minimise the inconvenience to daily commuters, the MeECL has begun laying the concrete surface on the Umiam dam in a zigzag manner.
The concrete surface idea was proposed by IIT Guwahati which was adopted by the MeECL.
Since the concrete surface would require 28 days to cure, the MeECL decided to do the concrete surfacing in a zigzag manner.
MeECL is expecting the rehabilitation work to be completed by August-end.

spot_imgspot_img

Related articles

Gaurav Gogoi-Pakistan links: SIT probing 38 individuals, says Assam CM

Guwahati, Sep 15: Assam Chief Minister Himanta Biswa Sarma, on Monday, intensified his criticism of Congress MP Gaurav...

US Chief Negotiator arriving in New Delhi to resume trade talks, govt set to finalise Export Promotion Mission

New Delhi, Sep 15: Amid the thaw in India-US relations, American Chief Negotiator Brendan Lynch is set to...

India, EU to hold 14th round of free trade agreement talks in Brussels from Oct 6-10

New Delhi, Sep 15: India and the European Union will hold the 14th round of negotiations for a...

Body of missing 4-yr-old girl recovered

Shillong, Sept 15: The body of a four-year-old girl, Insaphira Lyngdoh Mawna of Nongrah Nonglum, was recovered on...