Mawiong ISBT likely by Dec 2018

Date:

Share post:

spot_imgspot_img

SHILLONG: The upcoming Inter State Bus Terminus (ISBT) at Mawlai Mawiong has been delayed by 31 months and the new deadline for completion of the project is December 2018.
The project was sanctioned on January 28, 2013, and the scheduled date for completion was March 2015. The project is being taken up at a cost of Rs 48 crore with North Eastern Council (NEC) share of Rs 43 crore.
The first three installments of almost Rs 11 crore have been utilised and the fourth tranche of Rs 10 crore was issued on September 18 this year.
The project is aimed at decongesting the overcrowded parking lots located in Shillong since most parking places are used by inter-state buses and would accommodate 150-200 buses.
Meanwhile, the ISBT in Tura has been completed for almost a year but it is still awaiting its formal inauguration.

spot_imgspot_img

Related articles

Three arrested for gang-raping woman in Bhubaneswar hotel

Bhubaneswar, Sep 14 : Three persons have been arrested in connection with the gang-rape of a woman, who...

Raipur likely to adopt Police Commissioner System from November 1

Raipur, Sep 14: In a significant administrative overhaul, Raipur (Chhattisgarh) is set to implement the Police Commissioner System...

Counter-terrorist mock exercise at Delhi Airport to test crisis preparedness

New Delhi, Sep 14 : Delhi’s Indira Gandhi International Airport on Sunday witnessed a large-scale Joint Counter Terrorist...

CM Stalin calls ‘Mupperum Vizha’ show of unity ahead of 2026 Assembly elections

Chennai, Sep 14:Chief Minister of Tamil Nadu and DMK president M.K. Stalin has said that the upcoming 'Mupperum...