Partial report on Assembly dome collapse submitted

Date:

Share post:

spot_img
spot_img

SHILLONG, July 14: A five-member team of the Indian Institute of Technology Guwahati (IITG) has submitted the preliminary report to the PWD (Buildings) after auditing the left wing of the under-construction Assembly building at New Shillong Township.
A senior official of the PWD (Buildings) told The Shillong Times on Thursday that the IITG found the structure of the new Assembly building intact. The collapse of the dome did not damage the wing apart from causing minor cracks, he said.
“The team will take some more time to submit its final audit report,” he said, adding that the team has started assessing the dome portion of the building.
The report on the dome is expected to be submitted within two months after a thorough analysis.
The PWD had signed the probe agreement with the IITG to conduct a “non-destructive” test on the safety and stability of the entire building except the dome portion.

spot_img
spot_img

Related articles

Manipur Governor discusses state’s situation with HM Amit Shah

New Delhi/Imphal, Jan 18: Manipur Governor Ajay Kumar Bhalla on Saturday met Union Home Minister Amit Shah in...

Special prayers held for Saif Ali Khan at Ajmer Sharif Dargah

Ajmer, Jan 18: Special prayers were offered at the dargah of Khwaja Moinuddin Hasan Chishti in Ajmer for...

Pakistan: Over 1000 families in Kurram district set to be relocated to makeshift camps

Peshawar, Jan 18: The local administration in the Kurram District of Pakistan's restive Khyber Pakhtunkhwa (KP) province on...

India Open 2025: Indian challenge ends as Satwik-Chirag go down in semi-finals

New Delhi, Jan 18: India’s challenge at the Yonex-Sunrise India Open 2025 came to an end as men’s...