New Delhi, March 21: A Parliamentary panel has expressed concern over the fact that against the overall target of 40 GW, only 7.40 GW of rooftop solar projects have been installed in the country, and has asked the government to adhere to strict timelines while approving applications for such projects.

The Parliamentary Standing Committee on Energy, in its report on demands for grants for 2023-24 for the Ministry of New and Renewable Energy, which was tabled in Parliament on Tuesday, recommended that a strict timeline should be imposed for approval or rejection of applications and installation of net-meter as well as inspection of the system by distribution companies.

Also the distribution companies should mandatorily provide reasons behind rejection of applications on the national portal, the panel said.

It also suggested that distribution companies may be incentivised so that their apprehensions regarding losing their high-paying consumers because of installation of solar roof-tops are addressed and they positively participate in the programme.

IANS

spot_imgspot_img

Related articles

VPP slams MDA move for Education Grant

By Our Reporter SHILLONG, Aug 19: The Voice of the People Party (VPP) on Tuesday launched a scathing attack...

Army personnel and others carry out a search and rescue operation at cloudburst-hit Chisoti village

Army personnel and others carry out a search and rescue operation at cloudburst-hit Chisoti village, in Kishtwar district...

Detect, deport all illegal migrants: NESO to CM

KHADC MDCs call for meeting with traditional heads to prevent influx from Assam, Bangladesh By Our Reporter SHILLONG, Aug 19:...

Complete work on Rilbong-Baniun road by Dec: Metbah to NHIDCL

By Our Reporter SHILLONG, Aug 19: Meghalaya State Planning Board Chairman Metbah Lyngdoh has urged the National Highways and...